Interstate Bridge tolls on I-5: committee picks three rate options for a 2028 start

A Washington and Oregon tolling subcommittee on Friday, Nov. 20, recommended three rate options for the I-5 Interstate Bridge between Portland and Vancouver. Car tolls would run from $1.55 or $1.65 off-peak to $3.65 or $3.90 at rush hour, with tolling planned from mid-2028.

The Bi-State Tolling Subcommittee's options now go to the full Washington and Oregon transportation commissions, which set the actual rates, KGW reported. All three charge more at peak hours. Two of them start at $1.55 to $3.65 and step up to $1.65 to $3.90 when the new bridges open. The third starts at $1.65 to $3.90 with no step-up and uses only two price levels on weekends. Each adds 2.15% a year for inflation. They differ on when a 50% discount for low-income drivers would begin.

Trucks would pay a multiple of the car toll. In a June presentation to the two commissions, the rate options that match these numbers charged trucks 1.5 or 3 times the car rate, depending on the truck, while a dropped option used 2 and 4 times. KGW did not report truck rates from Friday's meeting, so the multipliers are not confirmed. At 3 times, a $3.90 rush-hour toll would come to $11.70 per crossing.

The commissions meet jointly in February, plan to release draft rates for public comment in late spring or early summer 2027 and adopt final rates in late 2027, according to KGW. Tolls would start on the current twin bridges as construction begins, about six months later. The June planning assumed a July 1, 2028 start, WSDOT as toll operator and free crossings from 11 p.m. to 5 a.m. during construction.

Tolls are expected to cover about $1.5 billion of a project now estimated at $14.4 billion. The I-205 Glenn Jackson Bridge will stay free because the program has no authority to toll it. A project memo in June indicated the I-5 crossing could lose about a third of its traffic once tolling starts, KGW reported.

Why it matters: Carriers that cross the Columbia on I-5 should budget for a toll from mid-2028 and follow the 2027 public comment period, when truck rates get set. I-205 stays toll-free, and planners expect part of the I-5 traffic to move there.